Taking over of the Site after completion of Civil Works – Package 04C
The construction works of Package 04C have been completed and taken over by PMU on 13th November 2023 at the Site. Mr. R M S Bandara (PD, RLVMMP), officials from the …
The construction works of Package 04C have been completed and taken over by PMU on 13th November 2023 at the Site. Mr. R M S Bandara (PD, RLVMMP), officials from the …
Procurement of Laboratory and Field Equipment for NBRO SPN Reference/Tender No.: RLVMMP/GOODS/NCT/04R-LOT 1/2/3/4/5/6/7/8
ECMWF 10-Day Rainfall & Temperature Forecast Based on 02 November 2023
ECMWF 10Day Rainfall Temperature Forecast 28 October 2023
The selected contractor for landslide mitigation works in Package 05D (RLVMMP/WORKS/05D), M/s Edward & Christie (Pvt.) Ltd. took over the sites on 18th and 19th October 2023. The work consists …
The selected contractor for landslide mitigation works in Package 05C (RLVMMP/WORKS/05C), M/s Sanguine – Sri Ram JV took over the sites on 17th October 2023. The work consists of constructions …
The mitigation completed site, Site No: 026 Gangarama Viharaya, Athelthota, Kalutara in Package 02 was handed over to the following responsible parties on 13th October 2023. Chief monk of Gangarama …
The mitigation completed site, Site No: 027 Sri Abinawarama Viharaya, Lihiniyawa, Kalutara in Package 02 was handed over to the following responsible parties on 13th October 2023. • Chief monk …
Problem-solving discussion and joint field visit to Lewella Gangarama Temple and Aniwatta Tunnel was conducted on 28th September 2023. The aim of the visit was to discuss the District Secretary’s …
Rainfall & Temperatures Forecast – 03 October 2023