Taking over of the Site after completion of Civil Works – Package 04A

The construction works of Site No: 020 – District Court Complex, Kegalle and Site No: 007 – Bus Stand Complex, Polgahawela under Package 04A have been completed and taken over by PMU on 13th November 2023 at the Sites.

Mr. R M S Bandara (PD, RLVMMP), officials from the PMU and NBRO, Add. District Secretory – Kegalle, representatives from Divisional Secretariat – Kegalle/Polgahawela, Municipal Council – Kegalle, Pradeshiya Shaba – Kegalle/Polgahawela, Executive Engineer – RDA Kegalle, Director – Disaster Management Division – Kegalle and representatives of the contractor, M/s Geo-Engineering (Pvt.) Ltd. were joined to this Handing / Taking over event.

Site No: 020 – District Court Complex, Kegalle

 

Site No: 007 – Bus Stand Complex, Polgahawela