The construction works of Package 2 have been completed and substantially taken over by PMU on 31st August 2022 and 07th September 2022.
The PMU team headed by Project Director Mr. R M S Bandara, officials from the construction supervision consultancy team and representatives of the contractor, M/s Sanguine – Sri Ram JV were joined to this Handing / Taking over event. The some of key beneficiaries of each site also participated to witness this event.
Some of the Photographs taken at each site are listed below.
Site No: 006 – Kumari Kanda
Site No: 013 – Kalavana