The selected contractor for landslide mitigation works in Package 05D (RLVMMP/WORKS/05D), M/s Edward & Christie (Pvt.) Ltd. took over the sites on 18th and 19th October 2023. 

The work consists of constructions such as soil nailing, retaining walls, horizontal drains, reshaping & turfing, and surface drains, as slope rectification measures in the following sites.

# Site No Site Name
1 030 Kalalgamuwa
2 037 Raththota Public Playground
3 038 Atanwala village – L1, L2, L3
4 039 Welikanda road, Balakaduwa
5 093 CEB Ukuwela Power Plant (Location 01)
6 098 CEB Ukuwela Power Plant (Location 02)

 

 

 

 

 

 

 

The CEB Chief Engineer – Kandy District, Chief Engineer – CEB Ukuwela Power Plant, Grama Niladhari and the site beneficiaries of the respective locations were joined during this event.