The selected contractor for landslide mitigation works in Package 05C (RLVMMP/WORKS/05C), M/s Sanguine – Sri Ram JV took over the sites on 17th October 2023.
The work consists of constructions such as soil nailing, retaining walls, horizontal drains, reshaping & turfing, and surface drains, as slope rectification measures located in the following sites.
| # | Site No | Site Name |
| 1 | 034 | St. Bernadette School |
| 2 | 041 | Walpola (Location 01) |
| 3 | 047 | Pallekanda, Delwita |
| 4 | 061 | Walpolakanda North Upper Colony |
| 5 | 069 | Dodamdeniya |
| 6 | 094 | Harasgama |
| 7 | 095 | Watagoda Hulangamuwa Road |
| 8 | 096 | Walpola (Location 02) |
The Principal of St. Bernadette School, Grama Niladhari and the site beneficiaries of the respective locations were joined during this event.