Implementation Review Mission for the Reduction of Landslide Vulnerability by Mitigation Measures Project (RLVMMP) was conducted from 10th July to 14th July 2023. The mission was led by Mr. Tomás …
Site Visit with Senior Social Development Specialist at AIIB, Mr. Susrutha Goonasekera was conducted on 26th June 2023 and 27th June 2023. Representing the PMU, Mr. H.M.L.Indrathilaka -Snr. Geologists and …
The bid opening of RLVMMP/WORKS/05A, RLVMMP/WORKS/05C and RLVMMP/WORKS/05D was held at NBRO Auditorium at 14.00 Hrs on 31st May 2023. Ten bidders have submitted their bids for each Tender and …
The Pre-bid meeting for the Tender RLVMMP/WORKS/05A, RLVMMP/WORKS/05C, and RLVMMP/WORKS/05D was held on 11th May 2023 at the NBRO Auditorium. The project Director chaired the meeting. The Officials of PMU …
The construction works of Package 04B have been completed and a site inspection visit was done by PMU on 14th May 2023. The PMU team headed by Project Director Mr. …
The pre-bid site visit at the following sites under Package-5D of Phase II was done successfully on 09th May 2023. The representatives from ten (10) civil engineering contractor organizations and …
The pre-bid site visit at the following sites under Package-5C of Phase II was done successfully on 08th May 2023. The representatives from twelve (12) civil engineering contractor organizations and …
The pre-bid site visit at the following sites under Package-5A of Phase II was done successfully on 10th May 2023 by answering each & every technical issue raised by the …
The selected contractor for landslide mitigation works at Nursing Training School, National Hospital, Kandy – Package 05B (RLVMMP/WORKS/05B), M/s RR Constructions (Pvt.) Ltd. has taken over the site on 04th …